Traffic Impact Bulletin 3
College Avenue and S.W. 30th Street Projects
Monday, March 4th, 2013 – Sunday, March 10th, 2013
The following construction schedule is subject to change due to unforeseen circumstances and/or weather conditions.
S.W. 30th Street from College Avenue to University Drive
Installation of the reuse line over the N-8 Canal is in progress. A new alignment has been approved and all necessary permits and approvals should be obtained by Tuesday March 5th, 2013.
A new maintenance of Traffic (MOT) plan has been submitted to continue construction to University Drive. The construction will require the shutdown of the westbound lanes from University Drive to approximately 200 feet east of the intersection. Construction activity will be limited to night shifts starting after 7:00 p.m. and ending at 6:00 a.m. to minimize the traffic impacts and is anticipated to commence this week.
College Avenue from S.W. 30th Street to Nova Drive
Northbound College Avenue will remain closed from S.W. 30th Street to Nova Drive. The contractor is investigating underground conflicts and will be doing low impact work. Drainage structures are on order and the installation of piping and drainage structures is anticipated for the week of March 11th.
|